Harworth R-Evolution Phase 4

Client Name

Harworth Group

Location

Waverley

Duration

65 Weeks

Completion

27/10/2023

Project Overview

Share Article:

Lindum built three buildings, ranging from 15,000 to 40,000 sq ft as part of the fourth phase of R-evolution, within Waverley’s Advanced Manufacturing Park.

The contract also included more than 200m of main infrastructure road to serve the new units and future development.

The units (numbers 8,9 & 11) were built for occupation by industrial, manufacturing and R&D businesses. Sustainability was a key feature of the buildings, with EV charging points, a rainwater harvesting system, and a sustainable heating and cooling system installed.

They also featured solar panels across 12 per cent of the roofs, with provision to allow future occupiers to increase this to 100 per cent.

The project was a real group effort for Lindum, with Plant, Security, LWR and KGM Roofing divisions supporting Lindum York with construction work.